WWTP start-up, seeding and operator training
A correct start-up determines how well your wastewater treatment plant (WWTP) will work for years to come. You can manage the start-up yourself with our online guide, we can advise you by phone or via WhatsApp, and if needed, a technician will come in person.
On this page
How start-up works
- Placement check: tank level, inlet and outlet connections, drainage vent, and the air blower’s cabinet and electrical protection
- Filling with water to the operating water level
- Starting the blower and adjusting the air distributor: aeration, sludge recirculation by the airlift pumps and surface skimming
- Seeding with activated sludge from a working plant or with a bacterial additive, so that the bacteria in the plant multiply faster
- Operator training: a walk-through of how the plant works, what to check regularly, what does not belong in it and how to keep the operating log (prevádzkový denník)
- Documents: operating manual (prevádzkový poriadok), operating log, warranty terms and commissioning report
Establishment period
The bacteria in the plant multiply gradually. A WWTP usually reaches full treatment efficiency after several weeks. During this period the effluent may be slightly cloudy and foam may appear on the surface, which is normal. In winter the establishment period takes longer, because bacteria work more slowly at lower temperatures.
We recommend having the first sample analysed only once the plant has become established.
In the first few weeks
- Use the plant normally, as the bacteria need a flow of wastewater.
- Do not switch the blower off.
- Do not use large amounts of chlorine-based or aggressive cleaning products.
- Do not pour fats or oils down the drain.
- If something does not seem right, write to us or send a photo via WhatsApp.
Cottages and seasonal properties
If you do not use the plant in winter, we will agree on how to run it, depending on the type of WWTP. In spring we check it, adjust it and, if needed, seed it again.
Price
We will send you the price of a start-up with a technician in a non-binding quote. We can also arrange a consultation by phone or via WhatsApp without a call-out.
Frequently asked questions
When can I start using the plant?
Straight after start-up. The bacteria multiply during normal use.
Do I need to buy bacteria?
At start-up, seeding with sludge or a starter product helps. In normal operation the plant does not need them. You will find these products in the ekotovar.sk online shop (in Slovak), in the Baktérie do ČOV category (WWTP bacteria).
Can I start up the WWTP myself?
Yes, by following the guide and with our advice by phone or via WhatsApp. If you are not sure how to set the air distributor, a technician will come in person. Check the warranty conditions in your plant’s documentation.
When are the first service and the first inspection due?
A follow-up visit once the plant has become established, then a service at least once a year. A technical inspection (technická revízia) must be arranged once a year, or once every two years if the plant has remote monitoring. More →
Why choose Bednár Montáže
- Certified inspection technicianInspections are carried out by Daniel Bednár, who is on the Slovak University of Technology (STU) list of inspection technicians.
- Service after the warranty, tooWe look after your plant for years after start-up.
- Paperwork in orderA report and an operating log entry after every visit.
- Parts from our own online shopAir blowers, diaphragms and additives, average delivery 2.6 days.
- All of SlovakiaWestern Slovakia regularly, elsewhere by agreement. Advice also online via WhatsApp.
- Since 200026 years of experience with wastewater treatment plants.
Book a WWTP start-up
Write to us once your plant is in place, and we will agree on the next steps. +421 905 229 394