Hydrogeological assessment for a wastewater treatment plant

If the water from your wastewater treatment plant (WWTP) cannot flow into a stream, the remaining route is into the groundwater through a soakaway. In that case the authority requires a hydrogeological assessment (hydrogeologický posudok). We explain what it contains, when you need it and how to prepare for it.

On this page

When an assessment is needed

Treated water from a small WWTP is preferably discharged to surface waters. It may go to groundwater only when discharge to a watercourse is not possible, and then only through a soakaway.

You will therefore mainly deal with a hydrogeological assessment in these cases:

  • there is no stream, roadside ditch or other suitable receiving watercourse near the plot
  • the watercourse administrator (správca vodného toku) does not agree to the discharge
  • the district office (okresný úrad) asks for it in the permit proceedings

If you discharge to a surface watercourse, an assessment is usually not required. The specific requirements are always set by the district office, department of environmental care (odbor starostlivosti o životné prostredie).

What the assessment looks at

The expert assesses whether the plot can take the water safely and whether there is any risk to groundwater or to wells in the area.

What is examinedWhy it matters
Geological layersGravel takes water differently from clay
Groundwater levelThe soakaway must be sufficiently above it
Permeability of the subsoilIt determines the size of the soakaway
Direction of groundwater flowIt shows where the water will flow
Wells and water sources nearbyThey require a safe distance
Protected areasThey can tighten the requirements or rule out a soakaway

The result is an expert opinion on whether a soakaway is possible, with a recommendation on its type and dimensions. The design then builds on the assessment.

How the assessment is prepared

  1. Gathering information. The expert looks at maps, geological data and information about the surrounding area.
  2. Site visit. The terrain, the location of wells and a possible soakaway site are checked.
  3. Trial pit and percolation test. If necessary, a trial pit is dug and the rate at which the soil takes up water is measured.
  4. Writing the assessment. The results are compiled into a document for the district office.

The assessment is prepared by a qualified person in hydrogeology. We can arrange it for you together with the design.

What documents to prepare

The work will go faster if you have the following to hand:

  • a land register extract (výpis z listu vlastníctva) and a copy of the cadastral map
  • a site plan of the plot showing the house and the proposed treatment plant
  • information about your own well and your neighbours’ wells
  • the number of people and the type of treatment plant
  • photos of the plot, especially of the planned soakaway site

If the assessment rules out a soakaway

An unfavourable result is not the end. You can look for solutions in several directions:

  • check another spot on the plot
  • choose a different type of soakaway
  • find a way to discharge to a surface watercourse
  • consider a plastic cesspool (sealed holding tank) if there really is nowhere to discharge the treated water

With a high water table or clay subsoil, a soakaway tends to be more difficult. Our guide to excavation and placement explains what to watch out for when the tank is placed where the groundwater is high.

Tip: Sort out the assessment before you order the plant. The result can affect the location, the category and the total cost.

Operation after the permit

For discharge to groundwater from sources of up to 50 population equivalents (PE, Slovak EO), 2 samples a year are usually taken, unless the permit specifies otherwise. It must always be possible to take a sample, so an inspection chamber is usually added to the soakaway. The limits for discharge to groundwater are stricter than for a watercourse.

When to order the assessment

The assessment belongs at the start of the whole process. The right order is:

  1. check whether discharge to a watercourse is possible
  2. find out which part of the plot is suitable for a soakaway
  3. order the assessment
  4. complete the design based on its result
  5. submit the permit application to the district office
  6. order the plant and start the excavation

If you do it the other way round and buy the plant first, the assessment may recommend a different location or a different category.

How to prepare the plot for a trial pit

If a trial pit or a percolation test is to be carried out, make the spot accessible. Remove obstacles, mark out underground utilities and arrange access to water if the test needs it. The test only makes sense at the spot where the soakaway will actually be.

Common problems with infiltration

Clay subsoil

It takes up water slowly. The soakaway tends to be larger, or another drainage route is sought.

High water table

The soakaway must be above it. On some plots this is quite difficult.

Wells nearby

Both your well and your neighbour’s well must be at a safe distance.

Small plot

On small plots it can be hard to keep the required distances.

Protected area

It can tighten the conditions or rule out a soakaway.

In any of these situations, it pays to get advice before you buy the plot or start building.

Frequently asked questions

Do I need an assessment if I discharge to a stream?

Usually not. The assessment mainly concerns discharge to groundwater. The district office will make the final decision.

Who prepares a hydrogeological assessment?

A qualified person in hydrogeology. We can arrange it for you together with the design of the plant.

Can the assessment affect my choice of plant?

Yes. It can determine where the water may be discharged, and so indirectly also the required category of the plant.

Why choose Bednár Montáže

  • Since 200026 years of experience with wastewater treatment plants.
  • Everything from one companySales, design, permit, guides, service, inspection and parts.
  • Certified inspection technicianInspections are carried out by Daniel Bednár, who is on the Slovak University of Technology (STU) list of inspection technicians.
  • All of SlovakiaWestern Slovakia regularly, elsewhere by agreement. Advice also online via WhatsApp.

Need an assessment for your treatment plant?

Send us the town or village and the plot number, and we will arrange the design and the assessment. +421 905 229 394