Infiltrating treated water from a wastewater treatment plant
Many plots have no stream into which treated water could flow. The solution is often a soakaway.
5 min readA domestic wastewater treatment plant (WWTP) cannot simply be bought and buried. The law treats it as a water structure (vodná stavba), so you need a permit from the district office (okresný úrad) and supporting documents that must be prepared in advance. This article is based on the wording of the laws available in November 2026, and we point out where you should check the procedure with the authority.
The Water Act (Act No. 364/2004 Coll.) classifies wastewater treatment plants as water structures and makes no exception for domestic plants (Section 52). The decision is made by the state water authority (orgán štátnej vodnej správy), which for a domestic WWTP is the district office, department of environmental care (odbor starostlivosti o životné prostredie). For water structures, it also acts as the special building authority (špeciálny stavebný úrad), see Section 26(3). The municipality does not issue the discharge permit.
You need to obtain two things, one building on the other:
The permit for the water structure can only be issued after the discharge permit or together with it (Section 21(2) and Section 26(1)).
New house: If the WWTP is part of a group of structures, i.e. structures that function as a whole, and a different building authority (stavebný úrad) is responsible for the main building, usually the municipality, that authority decides on the construction project. The district office then has the status of an authority concerned (Section 26(3) of the Water Act, Section 48(2) of the Building Act). The discharge permit, however, is always issued by the state water authority. Check with the district office whether this applies to you.
The Building Act (Act No. 25/2025 Coll.) has applied since 1 April 2025 and, for water structures, refers to the special building authority. Act No. 243/2026 Coll. amends it with effect from 1 January 2027. So before you submit your application, check the exact procedure for a domestic WWTP with the district office.
The application is accompanied by annexes with the data the office uses to assess the impact on water conditions. If the permit is also to serve as the decision on the construction project, further documents are added (Section 73(2) of the Water Act, Section 50(2) of the Building Act):
The office may also request further documents and expert opinions. The applicant bears the cost of expert opinions (Section 73(13)). The office also checks whether you have a right to the land that allows the construction work (Section 57 of the Building Act). If a pipe is to run across someone else’s land, sort this out in good time. We will prepare the design documentation for you.
Both the documents you need and the validity of the permit depend on this (Section 21(4)). Government Regulation No. 269/2010 Coll. gives priority to surface waters; water is discharged into groundwater through a soakaway only where this is necessary (Section 5a(7)). Sampling must always be possible.
| Condition | Into surface waters | Into groundwater |
|---|---|---|
| Permit validity | up to 10 years | up to 6 years |
| Sample analyses | 1 sample per year | 2 samples per year |
| Additional requirement | involvement of the watercourse administrator | prior investigation |
The permit sets the scope of the analyses.
Under Section 37(1), the permit can only be issued after a prior investigation, which only a person authorised under the Geological Act may carry out. It assesses the hydrogeological conditions, the self-purification capacity of the soil and rock and the risk of groundwater pollution. These questions are answered by a hydrogeological assessment (hydrogeologický posudok), which we will prepare for you.
There is an exception for domestic sewage from isolated dwellings that cannot be connected to the public sewer, provided they lie outside the protection zones of drinking water sources (Section 37(5)). However, the law does not explain what an “isolated dwelling” (osamotené obydlie) is. Check with the district office whether the exception applies to you and whether the office will ask for an assessment anyway.
The watercourse administrator (správca vodného toku) is always a party to proceedings on a permit that concerns surface waters (Section 73(3)). However, we have not found an obligation to submit their separate consent in the provisions on discharge. Before you apply, check whether your district office wants the administrator’s statement with the application. Check the same if the outfall pipe extends into the watercourse or onto the land along its bank.
The permit sets the permissible pollution values, and the plant must meet them. Small WWTPs are divided into categories under Government Regulation 269/2010:
| Category | What the plant can handle |
|---|---|
| I | organic pollution |
| II | nitrification as well |
| III | nitrification and denitrification, for example for protected water management areas |
| +P | phosphorus removal in addition |
| +D | disinfection in addition |
The limits also depend on where the water is discharged. For category II, the limit for ammonium nitrogen (NH4-N) is 30 mg/l for surface waters and 20 mg/l for groundwater. So check the required category with the district office before you order a plant. The WWTP must have CE marking and a declaration of performance under the standard STN EN 12566-3. You will find an overview on our treatment plants page and in the article How to choose a WWTP.
The office has to decide within 60 days of the start of the proceedings, or within three months in particularly complex cases (Section 73(8)). Allow extra time for preparing the documents.
You must notify the building authority that work is starting (Section 30 of the Building Act). The plant may be used on the basis of an occupancy certificate (kolaudačné osvedčenie). If the district office decided on the construction project, it also carries out the final approval (kolaudácia), Section 26(3) and (4).
The permit for building a small WWTP is only issued for a limited period. If a public sewer has been built and put into operation in the area, the permit is not renewed when it expires (Section 36(4)). The office may renew the discharge permit if the conditions under which it was issued have not changed (Section 21(5)).
After start-up, you operate the plant in line with the office’s decision, the operating manual (prevádzkový poriadok) and the manufacturer’s recommendations. You will also need a technical inspection (technická revízia), and you must keep an operating log (prevádzkový denník).
Expect to need a permit. For treatment plants, the Water Act requires both a permit for a water structure and a discharge permit. The Building Act explicitly lists cesspools (sealed holding tanks) among minor structures, but not treatment plants. From 1 January 2027, a notification will be possible for an underground structure made from a placed, assembled product with a floor area of up to 50 m² and a depth of up to 3 m. The law does not say whether this can also apply to a WWTP, so check with the district office.
As a rule, no. Where a public sewer has been built, a small WWTP may only be used if connecting to it would be unreasonably costly in technical or economic terms (Section 5a(4) of Government Regulation 269/2010).
A permit is also required to alter a water structure and to remove it. For building alterations, a notification is enough, but the office may decide that a decision on the construction project is needed (Section 26(1)). The district office will confirm what applies in your case.
If it was permitted under older regulations, you must apply by 31 December 2032 to bring the discharge permit into line with current rules (zosúladenie povolenia), Section 80f(2).
Sources: Act No. 364/2004 Coll., Act No. 25/2025 Coll., Government Regulation No. 269/2010 Coll.